Wired Real Estate
← States

Texas

The busiest state for gigawatt-scale announcements, with cheap land, a state sales tax exemption up to 20 years, and an ERCOT queue so large the state paused new interconnections in August 2026.

Tracked projects
18
Announced capacity
36.6 GW
Grid operator
ERCOT
Sales tax exemption
Yes

Why developers come here

Texas has more announced gigawatt-scale campuses than any other state, and the reasons stack up. Land in West Texas, the Panhandle, and the counties ringing Dallas-Fort Worth and Austin is flat, large-parcel, and cheap relative to Virginia or Arizona. Much of it sits near gas supply and existing or planned transmission. Average industrial electricity cost 6.12 cents per kWh in 2024 (EIA), about a quarter below the national average, and 6.65 cents per kWh year-to-date through June 2026.

The state exempts qualifying data centers from the 6.25 percent state sales tax on servers, cooling, generators, and, with a use study, electricity, for 10 to 20 years. And ERCOT, the grid operator for most of the state, is not under federal interconnection jurisdiction, which historically let developers move faster than in PJM or MISO. That speed advantage is now qualified: an interconnection queue of roughly 474 GW, about 90 percent of it data centers, triggered a statewide pause and audit in August 2026.

Incentives

Power

ERCOT covers roughly 90 percent of Texas load. The Panhandle and parts of the South Plains sit in SPP (Xcel Energy’s Southwestern Public Service), and El Paso is served by El Paso Electric in the Western Interconnection. Tracked projects in Amarillo, Pampa, and Abernathy are SPP-side; Meta El Paso is on El Paso Electric.

Inside ERCOT, large-load interconnection runs through a transmission utility (Oncor, CenterPoint, AEP Texas, TNMP) and ERCOT’s large-load process. Under SB 6 the PUCT published draft rule 16 TAC 25.194 in March 2026 for loads of 75 MW or more. As drafted it would require study fees of $100,000 (75 to 250 MW) or $300,000 (over 250 MW), financial security of $50,000 per MW, a non-refundable interconnection fee of $50,000 per MW after study, proof of site control, disclosure of parallel requests in other states, and quarterly progress reports. If a project withdraws, the utility keeps 80 percent of the security. A final rule is expected by December 31, 2026.

ERCOT’s “Batch Zero” study was meant to process the queue in one pass; the August 2026 audit pushed its first-batch completion target to about April 2027, with 250 to 300 projects to be reviewed. Developers with their own gas generation (Fermi America, CyrusOne Fairfield, Comanche Circle) are partly insulated, but SB 6 also gives ERCOT curtailment authority over co-located loads in emergencies. Water is now a legislative issue: the Senate Water, Agriculture and Rural Affairs Committee held an interim hearing on September 1, 2026 on data center water sourcing and whether brackish or produced water should be treated differently.

Where the projects are

Four corridors: the Abilene-Sweetwater-Colorado City stretch along I-20 (Stargate Abilene, IREN Sweetwater, Barber Lake, Stargate Frontier in Shackelford County); the Panhandle and South Plains (Fermi America near Amarillo, Meitner Energy Center near Pampa, Project Caprock at Abernathy, Google in Armstrong and Haskell counties, Crusoe/Lancium at Childress, QTS/Lancium in Hall County); Central Texas east of Austin and the Brazos valley (Stargate Milam County, CyrusOne Fairfield, CloudBurst San Marcos); and the Permian and far west (Microsoft Pecos, Project Horizon in Pecos County, Meta El Paso). Hood County, southwest of Fort Worth, has eight proposals including Comanche Circle.

Local politics

Resistance clusters where projects land in unincorporated areas, because Texas counties have no zoning authority. In Hood County, commissioners twice failed to pass a moratorium, then tightened development rules and revoked one approval, drawing developer lawsuits. At an August 19, 2026 legislative hearing at the Capitol that filled two overflow rooms, residents from Williamson, Leon, and other counties cited noise, lights, water, and electric bills; a Leon County commissioner said the core problem is “a lack of county regulatory authority over unincorporated areas.” The Office of Public Utility Counsel told lawmakers a gigawatt-scale data center should pay 100 percent of the new infrastructure it causes.

Projects have generally been welcomed in West Texas and Panhandle counties where the tax base is thin and the land is ranch or dryland farm, and where developers bring their own generation. The 2027 legislative session is expected to take up county authority, water disclosure, and cost allocation.

What a landowner should know

Developers typically seek 500 to 2,000 acres or more, contiguous, with an existing 138 kV or 345 kV line crossing or adjacent, or a substation within a few miles. Gas pipeline access matters for behind-the-meter projects. Option agreements of one to three years are the norm, often with confidentiality clauses; the Hood County fight shows how that secrecy plays locally.

Because counties cannot zone, the main local lever is the Chapter 312 abatement negotiation, which is also where conditions on water and noise get attached. Ask whether the project is in ERCOT’s Batch Zero and whether it has passed the 2026 audit. The state contact is the Texas Economic Development and Tourism Office in the Governor’s office; the sales tax certification runs through the Comptroller.

Tracked projects in Texas

Project Location Developer Capacity Status Announced Verified
Fermi America HyperGrid / Project Matador
for TensorWave (first binding lease, 222 MW expandable to 650+ MW)
Carson (some sources cite Randall), TX Fermi America (with Texas Tech University System) 17 GW Under construction Jun 26, 2025 Sep 17, 2026
Comanche Circle (Sailfish) Hood, TX Sailfish Digital Ventures 5 GW Rumored Jan 25, 2025 Sep 17, 2026
IREN Sweetwater Hub Nolan, TX IREN 2 GW Under construction Sep 8, 2026 Sep 17, 2026
Microsoft Pecos
for Microsoft
Reeves, TX Microsoft 2 GW Announced Jun 22, 2026 Sep 17, 2026
Project Horizon (Poolside West Texas)
for CoreWeave (anchor for phase one; partnership reported ended April 2026)
Pecos, TX Poolside (with Longfellow Ranch land) 2 GW Announced Oct 15, 2025 Sep 17, 2026
Stargate Frontier (Vantage, Shackelford County)
for Oracle / OpenAI (Stargate) per OpenAI release
Shackelford, TX Vantage Data Centers 1.4 GW Under construction Aug 19, 2025 Sep 17, 2026
CloudBurst San Marcos campus Hays, TX CloudBurst Data Centers 1.2 GW Rumored Feb 10, 2025 Sep 17, 2026
Stargate Abilene
for Oracle / OpenAI
Taylor, TX Crusoe 1.2 GW Under construction Jan 21, 2025 Sep 17, 2026
Stargate Milam County
for OpenAI
Milam, TX SB Energy (SoftBank Group) 1.2 GW Announced Sep 23, 2025 Sep 17, 2026
Crusoe / Lancium Childress campus
for Unnamed hyperscaler
Childress, TX Crusoe with Lancium 1 GW Announced Jul 15, 2026 Sep 17, 2026
Meta El Paso
for Meta
El Paso, TX Meta / BlackRock joint venture 1 GW Under construction Oct 15, 2025 Sep 17, 2026
CyrusOne Fairfield (Freestone Energy Campus) Freestone, TX CyrusOne (power and land from Calpine) 760 MW Permitted Aug 3, 2026 Sep 17, 2026
Project Caprock (Aligned) Hale, TX Aligned Data Centers 540 MW Under construction Apr 9, 2026 Sep 17, 2026
Barber Lake
for Fluidstack (entire 300 MW; Google backstop)
Mitchell, TX Cipher Mining 300 MW Under construction Sep 25, 2025 Sep 17, 2026
Google Armstrong County
for Google
Armstrong, TX Google Announced Nov 14, 2025 Sep 17, 2026
Google Haskell County
for Google
Haskell, TX Google Announced Nov 14, 2025 Sep 17, 2026
Meitner Energy Center (Google / Intersect)
for Google
Gray, TX Intersect (Google subsidiary since March 2026) Under construction Jun 4, 2026 Sep 17, 2026
QTS / Lancium Hall County campus Hall, TX QTS Data Centers (Blackstone) with Lancium Announced Jul 13, 2026 Sep 17, 2026

Sources

  1. Aug 19, 2026 Texas lawmakers hear from residents, state regulators on the impacts of data centers · CBS News Texas
  2. Aug 14, 2026 Texas will audit up to 300 projects, mostly data centers, before they can connect to the grid · The Texas Tribune
  3. Jun 2, 2026 The 8 data centers that could transform one Texas county · The Texas Tribune
  4. Mar 17, 2026 Texas Senate Bill 6 Update - What Data Centers and Large Load Customers Should Know About Proposed Interconnection Standards · Greenberg Traurig LLP
  5. undated State Sales Tax Exemption for Qualified Data Centers · Texas Comptroller of Public Accounts
  6. undated Texas Tax Code Section 151.359 - Property Used in Certain Data Centers; Temporary Exemption · Texas Public Law
  7. undated 34 Tex. Admin. Code 3.335 - Property Used in a Qualifying Data Center or Qualifying Large Data Center Project · Legal Information Institute
  8. undated Texas Senate Bill 6 Ushers in Major Overhaul of Large Load Interconnection and Grid Access Rules · Bracewell LLP
  9. undated Facing an estimated 474 GW of interconnection requests, Texas hits pause on data centers · Utility Dive
  10. undated Texas Senate Scrutinizes Data Center Water Usage · Holland & Knight
  11. undated JETI FAQ · Texas Comptroller of Public Accounts
  12. undated Average Price of Electricity to Ultimate Customers by End-Use Sector, by State, 2024 and 2023 (Electric Power Annual Table 2.10) · U.S. Energy Information Administration
  13. undated Average Price of Electricity to Ultimate Customers by End-Use Sector, by State, Year-to-Date through June 2026 and 2025 (Electric Power Monthly Table 5.6.B) · U.S. Energy Information Administration

Last reviewed Sep 17, 2026