CyrusOne Fairfield (Freestone Energy Campus)

Permitted

Texas · Freestone · last verified Sep 17, 2026

Developer
CyrusOne (power and land from Calpine)
Tenant
Location
Fairfield, Freestone, Texas
Announced capacity
760 MW
Capacity confidence
Reported, partly confirmed
Phase one
Site
Utility
Calpine Freestone Energy Campus (1 GW gas combined-cycle)
Power source
on-site gas (adjacent combined-cycle plant)
Reported investment
$1.5B
Announced
Aug 3, 2026
Target online
Completion expected end of August 2027

Notes

Three ~306,000 sq ft buildings; announced date is the permit-filing coverage date; $1.5B is permit-stated construction cost; original CyrusOne/Calpine announcement predates this and should be located.