Meta El Paso
Under constructionTexas · El Paso · last verified Sep 17, 2026
- Developer
- Meta / BlackRock joint venture
- Tenant
- Meta
- Location
- El Paso, El Paso, Texas
- Announced capacity
- 1 GW
- Capacity confidence
- Stated in primary source
- Phase one
- —
- Site
- —
- Utility
- El Paso Electric
- Power source
- grid, 100% matched clean/renewable
- Reported investment
- $14B
- Announced
- Oct 15, 2025
- Target online
- 2028
Notes
Initially announced as $1.5B and 'can scale to 1GW'; raised to over $10B in March 2026 and ~$14B total under the July 2026 BlackRock venture.
Location
Approximate coordinates: 31.7600, -106.4900 · open in OpenStreetMap
Sources
- Jul 28, 2026 Meta Announces New Strategic Venture With BlackRock to Develop Data Center in El Paso · Meta