Project Caprock (Aligned)
Under constructionTexas · Hale · last verified Sep 17, 2026
- Developer
- Aligned Data Centers
- Tenant
- —
- Location
- Abernathy, Hale, Texas
- Announced capacity
- 540 MW
- Capacity confidence
- Stated in primary source
- Phase one
- —
- Site
- 313 acres
- Utility
- Xcel Energy (SPS)
- Power source
- grid
- Reported investment
- —
- Announced
- Apr 9, 2026
- Target online
- First facility LBB-01 anticipated Q1 2027
Notes
Six facilities totaling 1.65M sq ft; $5B stated as regional economic infusion rather than capex, so left null.
Location
Approximate coordinates: 33.8300, -101.8400 · open in OpenStreetMap
Sources
- Apr 9, 2026 Aligned Data Centers Breaks Ground on Project Caprock, a 540 MW Data Center Campus in Northwest Texas · GlobeNewswire
See something wrong? Send a correction.