IREN Sweetwater Hub
Under constructionTexas · Nolan · last verified Sep 17, 2026
- Developer
- IREN
- Tenant
- —
- Location
- Sweetwater, Nolan, Texas
- Announced capacity
- 2 GW
- Capacity confidence
- Stated in primary source
- Phase one
- 300 MW
- Site
- 2,200 acres
- Utility
- ERCOT (conditionally included as Base Load in ERCOT Batch Zero)
- Power source
- grid
- Reported investment
- —
- Announced
- Sep 8, 2026
- Target online
- First 300 MW at Sweetwater 1 targeted Q4 2027
Notes
Sweetwater 1 is 1,400 MW on 1,700 acres and Sweetwater 2 is 600 MW on 500 acres; campus announced well before the September 2026 release used as dated source. County to confirm.
Location
Approximate coordinates: 32.4700, -100.4000 · open in OpenStreetMap
Sources
- Sep 8, 2026 IREN's 2GW Sweetwater Hub Included as Base Load in ERCOT Batch Zero · IREN via GlobeNewswire
- undated Sweetwater Data Center | 2,000MW AI Campus in Texas · IREN
See something wrong? Send a correction.