CloudBurst San Marcos campus
RumoredTexas · Hays · last verified Sep 17, 2026
- Developer
- CloudBurst Data Centers
- Tenant
- —
- Location
- San Marcos, Hays, Texas
- Announced capacity
- 1.2 GW
- Capacity confidence
- Estimate or generation figure
- Phase one
- —
- Site
- —
- Utility
- Energy Transfer (gas supply up to 450,000 MMBtu/day)
- Power source
- on-site gas (behind-the-meter)
- Reported investment
- —
- Announced
- Feb 10, 2025
- Target online
- H2 2026 if FID reached
Notes
1.2 GW is generating potential of contracted gas volume, not announced IT load; agreement contingent on FID with a customer, not confirmed.
Location
Approximate coordinates: 29.8800, -97.9400 · open in OpenStreetMap
Sources
- Feb 10, 2025 Energy Transfer and CloudBurst Sign Agreement for Natural Gas Supply to Data Center Project in Central Texas · Energy Transfer