Wired Real Estate
← States

New York

New York became the first state to freeze large data center permits in July 2026, even as nearly 12 GW of requests sit in the NYISO queue and upstate hydro sites like Lake Mariner keep building.

Tracked projects
1
Announced capacity
750 MW
Grid operator
NYISO
Sales tax exemption
Yes

Why developers come here

New York’s appeal is split in two. Downstate, Manhattan and the New York City suburbs are a legacy colocation and financial-services market where power is scarce and expensive. Upstate is where the AI-era interest is: Niagara hydro, retired coal and gas plant sites with existing 345 kV interconnections, cold weather that cuts cooling costs, cheap land, and industrial electricity that averaged 10.14 cents per kWh statewide in the first half of 2026 (EIA), with lower prices available in NYISO’s western zones.

The proof point is TeraWulf’s Lake Mariner campus in Barker (Niagara County), a former coal plant site with dual 345 kV lines, where Fluidstack has leased hundreds of megawatts backstopped by Google. Stream Data Centers proposed a $19.5 billion, 2.2 million square foot campus at the STAMP site in Genesee County.

The interconnection queue tells the story: NYISO went from six large-load projects totaling 1 GW in 2022 to 48 projects and about 12 GW at the end of 2025, most of them data centers and most in upstate zones D, E, and H. Then, on July 14, 2026, the state paused new large data center permitting.

Incentives

Power

New York has its own grid operator, NYISO. National Grid serves most of upstate including Niagara and Genesee counties; NYSEG and RG&E (Avangrid) serve the Southern Tier, Finger Lakes, and Rochester; Con Edison serves New York City and Westchester; the state-owned New York Power Authority owns the Niagara and St. Lawrence hydro plants and the main 345 kV backbone.

Loads above 10 MW connecting at 115 kV or higher (or above 80 MW at lower voltages) go through NYISO’s large-load process with a system impact study; smaller loads use the utility’s own procedures. NYISO is rewriting the process during 2026 to shorten studies, define milestones for inclusion in planning, and clarify modifications, with a target of a FERC filing in December 2026. In February 2026 the Public Service Commission opened the Energize NY Development proceeding to redesign large-load cost allocation, interconnection, and tariff structures, with a staff white paper to follow; no statewide large-load tariff has been adopted yet.

Downstate is capacity-constrained. Con Edison’s Zone J peaked near 10,000 MW in 2024, and the utility has revised its interconnection principles so large loads face the same substation, breaker-failure, and under-frequency load-shedding requirements as generators.

Where the projects are

Western New York is the center of gravity: Lake Mariner in Barker (Niagara County, tracked on this site), the STAMP site in the Town of Alabama (Genesee County), and the Buffalo-Niagara hydro corridor generally. The Finger Lakes have the Lansing plant site in Tompkins County. Downstate activity is incremental expansion of existing colocation in Manhattan, Long Island, and the Hudson Valley rather than new campuses.

Local politics

The STAMP fight defined 2026. Supporters, including Laborers’ Local 435, cited thousands of construction jobs, 125 permanent positions, private funding of electrical infrastructure, and PILOT revenue. Opponents, led by the Tonawanda Seneca Nation, the Sierra Club, and a local resident, cited noise audible for miles, wetlands and stormwater impacts on the adjacent reservation and the Iroquois National Wildlife Refuge, grid strain, and the size of the subsidy; they sued in July 2026 to void the 2012 incentive zoning agreement between the town and the Genesee County EDC. The executive order appears to halt Stream’s DEC permits.

Governor Hochul framed the moratorium as protecting “large job-creators” like Micron, saying data centers create far fewer permanent jobs per megawatt. Business groups and some upstate officials warned the pause could cost the state grid investments that developers had offered to fund. Niagara County has welcomed TeraWulf, whose Lake Mariner project reuses a coal site and predates the order.

What a landowner should know

For at least the next year, any new project of 50 MW or more that needs a DEC permit (wetlands, air, stormwater for large sites) is frozen, so expect option agreements rather than closings. Developers upstate have sought 100 to 500 acres near a 115 kV or 345 kV line, a retired plant site, or a shovel-ready park; downstate, only existing industrial buildings with power are realistic.

Local approvals still run through town planning boards and county IDAs, and IDA hearings on PILOTs are where opposition organizes. Ask whether the site is in a NYISO zone with headroom (western zones A through E) or a constrained one (J and K), and whether the project counts on NYPA hydro, which is increasingly unlikely.

The state agency is Empire State Development; the Public Service Commission’s Energize NY Development proceeding and NYISO’s large-load process will set the interconnection rules that apply once the moratorium lifts.

Tracked projects in New York

Project Location Developer Capacity Status Announced Verified
Lake Mariner Data campus
for Fluidstack (~360 MW, Google-backstopped); Core42
Niagara, NY TeraWulf 750 MW Under construction Aug 18, 2025 Sep 17, 2026

Sources

  1. Jul 16, 2026 Hochul: Data center moratorium an effort to protect large job-creators · Spectrum News
  2. Jul 15, 2026 Future of STAMP data center uncertain due to Hochul order, lawsuit · Investigative Post
  3. Jul 14, 2026 Executive Order No. 62, Establishing a Temporary Moratorium on Data Centers in New York While the State Develops Higher Standards for Data Center Development and Benefits Blueprint to Support Localities · Office of the Governor of New York
  4. Jun 2, 2026 Dial-Up Era Tax Break Could Cost New York on Data Centers · Syracuse.com via GovTech
  5. Apr 17, 2026 Massive Western N.Y. data center plan sparks heated debate · Spectrum News
  6. Feb 12, 2026 Governor Hochul Announces PSC Proceeding on Her Plan to Ensure Data Centers Pay Their Fair Share for Energy Grid Upgrades · Office of the Governor of New York
  7. Feb 9, 2026 NYISO Considers Revisions to Large Load Interconnection Process · Harris Beach Murtha
  8. Aug 18, 2025 TeraWulf Announces Fluidstack Expansion with 160 MW CB-5 Lease at Lake Mariner · TeraWulf
  9. Mar 2, 2012 Tax Bulletin ST-405, Internet Data Centers · New York State Department of Taxation and Finance
  10. undated New York Data Center Policy · Server Country
  11. undated Load and Capacity Data Report (Gold Book) · New York Independent System Operator
  12. undated Con Edison Large Load Planning Updates, NYISO TPAS July · Zero Emission Grid
  13. undated Electric Power Monthly, Table 5.6.B, Average Price of Electricity to Ultimate Customers by End-Use Sector, by State, Year-to-Date · U.S. Energy Information Administration

Last reviewed Sep 17, 2026