Wired Real Estate
← States

New Mexico

Home to the $165 billion Project Jupiter bond deal at Santa Teresa, New Mexico has the cheapest industrial power in the West but no statewide data center exemption and a fast-growing wave of county moratoria.

Tracked projects
1
Announced capacity
0 MW
Grid operator
Non-ISO (WECC) for PNM and El Paso Electric; SPP for Xcel's eastern New Mexico territory
Sales tax exemption
No

Why developers come here

New Mexico’s pitch is power price and land. Industrial electricity averaged 5.41 cents per kWh in the first half of 2026, the lowest of any state in the Mountain West, and large tracts of flat, sparsely populated land sit along the I-10 and I-25 corridors and around the Permian gas fields in the southeast. Meta operates a campus in Los Lunas, south of Albuquerque, which proved the state could deliver a hyperscale build.

The state’s incentive structure is unusual. There is no data-center-specific sales tax exemption. Instead, counties and cities issue industrial revenue bonds (IRBs) that abate property tax and exempt IRB-financed purchases from gross receipts and compensating tax for the life of the bond. That mechanism produced the largest incentive package in state history in September 2025, when Doña Ana County authorized up to $165 billion in IRBs for Project Jupiter at Santa Teresa, next to the Texas line and the El Paso metro. The same deal has since produced two lawsuits, a pipeline denial, and a wave of county moratoria.

Incentives

Power

PNM (now part of TXNM Energy) serves Albuquerque, Santa Fe, and most of the state’s population. El Paso Electric serves Las Cruces and Santa Teresa. Xcel’s Southwestern Public Service serves the eastern plains and the Permian and is the only New Mexico utility inside an organized market (SPP). PNM and El Paso Electric are in the Western Interconnection without an ISO, so interconnection is a bilateral utility process overseen by the Public Regulation Commission (PRC).

No large-load tariff has been approved yet. PNM told legislators in July 2026 that it will file one with the PRC later in 2026, including minimum revenue requirements and exit fees to protect residential customers, and the PRC has said it will convene a working group. Project Jupiter sidestepped the grid entirely with a private gas-fired microgrid reported at nearly 3,000 MW, but the Green Chile pipeline that would feed it was denied a crossing of state trust land by Land Commissioner Stephanie Garcia Richard in March and again in July 2026, and the pipeline’s own timeline has slipped to 2027.

Water is the recurring question. A researcher told legislators in September 2026 that the state’s data centers use just over 500 million gallons a year today, about half a percent of statewide use, but that the full pipeline of proposed projects would push that to roughly 23.6 billion gallons. Project Jupiter committed to closed-loop cooling averaging 20,000 gallons per day.

Where the projects are

Santa Teresa in Doña Ana County (Project Jupiter, developed by BorderPlex Digital Assets with STACK Infrastructure for Oracle and OpenAI) is the dominant site. Los Lunas in Valencia County hosts Meta. Albuquerque, Rio Rancho, and Bernalillo County have several proposals working through IRB conditions. Speculative pitches have surfaced in Grant County, Socorro County (a 10,000-acre proposal), and at Spaceport America.

Local politics

Doña Ana County approved Project Jupiter 4-1 on September 19, 2025 after hours of testimony and a confrontation between opponents and commissioners. Supporters pointed to 750 permanent jobs paying $75,000 to $100,000, 2,500 construction jobs, and PILOT revenue for a poor border county. Opponents cited water, gas plant emissions, and a process they said was rushed. The New Mexico Environmental Law Center sued in October 2025 to void the IRB ordinances; a judge denied the county’s motion to dismiss in March 2026, then dismissed the case in June 2026 with leave to re-file. A second suit filed February 6, 2026 alleges Open Meetings Act violations, and the state Supreme Court temporarily halted the project’s air permit hearing in August 2026.

That fight is why northern counties moved first on moratoria. Santa Fe County lowered its trigger from 100 MW to 1 MW after public comment. Lea County, in the oil patch, chose conditions rather than a ban, and Bernalillo County did the same. Utility executives have told legislators that large customers can pay for grid modernization; several legislators pushed back.

What a landowner should know

Because incentives are negotiated county by county, the county commission is the decision-maker here, not the state. Ask any prospective buyer whether they intend to seek IRBs and which county has been approached. Developers in southern New Mexico look for 500 acres or more with gas pipeline access as well as transmission, because private generation has become the default plan for very large loads. Around Albuquerque, 100 to 300 acres near existing PNM 345 kV lines is more typical.

Water rights are severed from land in New Mexico and must be transferred through the State Engineer, and LEDA money cannot be used to buy them, so a buyer will want to know exactly what rights convey. Option agreements of 12 to 24 months are common while a developer negotiates an IRB ordinance. The state contact is the New Mexico Economic Development Department, which administers LEDA and JTIP; IRB questions go to the county manager’s office.

Tracked projects in New Mexico

Project Location Developer Capacity Status Announced Verified
Stargate Project Jupiter (Santa Teresa)
for Oracle Cloud Infrastructure for OpenAI
Doña Ana, NM BorderPlex Digital Assets / STACK Infrastructure Under construction Sep 23, 2025 Sep 17, 2026

Sources

Last reviewed Sep 17, 2026