Stargate Project Jupiter (Santa Teresa)

Under construction

New Mexico · Doña Ana · last verified Sep 17, 2026

Developer
BorderPlex Digital Assets / STACK Infrastructure
Tenant
Oracle Cloud Infrastructure for OpenAI
Location
Santa Teresa, Doña Ana, New Mexico
Announced capacity
Capacity confidence
Estimate or generation figure
Phase one
Site
1,400 acres
Utility
Power source
on-site Bloom Energy fuel cell microgrid (up to 2.45 GW), replacing earlier planned gas turbines
Reported investment
Announced
Sep 23, 2025
Target online
Initial operations Q4 2026

Notes

$165B is the maximum industrial revenue bond authorized by the county, not confirmed capex, so left null; no MW disclosed; litigation by local groups pending. County commissioners approved $165B IRB cap 2025-09-19; Oracle confirmed as tenant and Bloom fuel cells announced 2026-04-27.

Location

Approximate coordinates: 31.8600, -106.6500 · open in OpenStreetMap