Stargate Project Jupiter (Santa Teresa)
Under constructionNew Mexico · Doña Ana · last verified Sep 17, 2026
- Developer
- BorderPlex Digital Assets / STACK Infrastructure
- Tenant
- Oracle Cloud Infrastructure for OpenAI
- Location
- Santa Teresa, Doña Ana, New Mexico
- Announced capacity
- —
- Capacity confidence
- Estimate or generation figure
- Phase one
- —
- Site
- 1,400 acres
- Utility
- —
- Power source
- on-site Bloom Energy fuel cell microgrid (up to 2.45 GW), replacing earlier planned gas turbines
- Reported investment
- —
- Announced
- Sep 23, 2025
- Target online
- Initial operations Q4 2026
Notes
$165B is the maximum industrial revenue bond authorized by the county, not confirmed capex, so left null; no MW disclosed; litigation by local groups pending. County commissioners approved $165B IRB cap 2025-09-19; Oracle confirmed as tenant and Bloom fuel cells announced 2026-04-27.
Location
Approximate coordinates: 31.8600, -106.6500 · open in OpenStreetMap
Sources
- Apr 27, 2026 Oracle, BorderPlex, and Bloom Energy to Power Project Jupiter with Fuel Cell Technology · Oracle
- Sep 25, 2025 New Mexico's Project Jupiter data center part of larger Stargate AI initiative · El Paso Matters
- undated Project Jupiter · Doña Ana County
See something wrong? Send a correction.