A 2025 law traded a longer equipment exemption for the country's strictest large-load rules, and a wave of lawsuits and county denials has since slowed a boom that never quite arrived.

Tracked projects
1
Announced capacity
708 MW
Grid operator
MISO
Sales tax exemption
Yes

Why developers come here

Minnesota offers a cold climate, abundant water, a MISO grid with strong transmission into the Twin Cities, and a stable utility (Xcel) with a large carbon-free portfolio that helps hyperscalers meet their own clean-energy targets. Meta built an $800 million campus on 280 acres at UMore Park in Rosemount; Microsoft and Amazon have projects at the former Sherco coal site in Becker; Google has proposed campuses in Hermantown and Pine Island; and Tract has a 340-acre, 12-building technology park approved in Farmington. More than a dozen projects have been announced.

What makes Minnesota different is that it decided in 2025 to write the rules before most of them were built. The state repealed its sales tax exemption on data center electricity, created a “very large customer” class at the Public Utilities Commission, and required every large-load contract to be reviewed publicly. Industrial power averaged 9.64 cents per kWh in the first half of 2026, and that plus organized local opposition has left several announced projects stalled.

Incentives

Power

Minnesota is in MISO. Xcel Energy serves the Twin Cities and most of the population; Minnesota Power serves the Duluth and Iron Range region; Otter Tail Power serves the west; Great River Energy supplies most cooperatives. Municipal utilities and cooperatives are exempt from the 2025 large-load rules.

Minnesota Statutes 216B.1622 and 216B.1623 (2025) require the Public Utilities Commission (PUC) to create a very-large-customer class for new loads of 100 MW or more (and “system intensive” loads of 20 to 100 MW), require data centers to pay for all system upgrades built to serve them, require service to stay on track with the state’s carbon-free-by-2040 benchmarks, and require every electric service agreement (ESA) with a large customer to be filed and reviewed at a public PUC meeting.

The PUC approved Xcel’s large-load tariff on May 15, 2026: a 15-year minimum contract, an exit fee equal to 80 percent of remaining demand charges, and a separate rate class for data centers in future rate cases. Minnesota Power has filed its own tariff and Otter Tail has said it will. Two ESAs are pending as of September 2026: Harmony Group LLC (Google) with Minnesota Power for Hermantown (docket 26-159) and Echo Zone LLC (Google) with Xcel for Pine Island (docket 26-170).

Where the projects are

Dakota County south of the Twin Cities is the center of gravity: Meta in Rosemount, Tract in Farmington, and proposals in Lakeville and Inver Grove Heights. Sherburne County (Becker) has Microsoft and Amazon on Xcel’s retiring coal site. Google’s two proposals are at Hermantown, outside Duluth, and Pine Island in Olmsted County. Southwest Minnesota’s Nobles County saw and rejected a $4 billion Geronimo Power proposal near Worthington.

Local politics

Farmington is the reference case. The city approved Tract’s 340-acre Farmington Technology Park in November 2024; eight residents and the Coalition for Responsible Data Center Development sued on November 29, 2024, alleging the rezoning violated an orderly annexation agreement with Castle Rock Township and citing water, noise, and power. A judge issued an injunction, Castle Rock Township filed its own suit in January 2025, and the case slowed the project for nearly two years. The coalition withdrew its suit on September 9, 2026, citing legal costs; the township’s suit appears to remain pending.

Hermantown’s council tabled Google’s abatement and development agreements in May 2026 after residents objected to the nondisclosure agreement that hid the company’s identity behind the code name “Project Loon” and to a tax break for a trillion-dollar company; three council candidates are running on the issue and Google has since scaled the project back. Nobles County commissioners rejected a zoning change for data centers on farmland in April 2026 and ended the environmental review after Geronimo Power withdrew. Rosemount and Becker moved quickly for the jobs and tax base, and the building trades are the most vocal statewide supporters.

What a landowner should know

Twin Cities-area campuses have run 280 to 340 acres; Google’s greater Minnesota proposals are smaller single-user sites. Proximity to an Xcel or Great River Energy 345 kV or 115 kV line is the first screen. Option agreements of 12 to 24 months are typical, and because every large-load contract now goes through a public PUC review with a 15-year commitment, buyers will want to see the utility path before closing. Expect a developer to ask for a nondisclosure agreement; a public-records request is how Google’s Hermantown role became known, so assume the deal will become public. Water appropriation permits come from the DNR, and township orderly-annexation agreements can give a neighboring township veto power over rezoning, as in Farmington. The state contact is DEED’s Data Center Program, which certifies facilities for the sales tax exemption.

Tracked projects in Minnesota

Project Location Developer Capacity Status Announced Verified
Tract Farmington Technology Park Dakota, MN Tract 708 MW Permitted Nov 18, 2024 Sep 17, 2026

Sources

  1. Sep 9, 2026 Coalition for Responsible Data Center Development withdraws lawsuit in Farmington due to litigation costs · Blandin on Broadband
  2. Jun 12, 2026 New data center regulations in Minnesota halted after pushback from unions, industry · MPR News
  3. May 5, 2026 Hermantown tables vote on key agreements for contentious Google data center · MPR News
  4. Apr 27, 2026 Minnesota's long-predicted data center boom is on shaky ground · Minnesota Reformer
  5. Apr 21, 2026 Nobles County board to vote on whether to allow massive data centers on farm land · MPR News
  6. undated Qualified Data Centers · Minnesota Department of Revenue
  7. undated New Laws 2025 - Omnibus tax bill (HF 1346 / Chapter 13) · Minnesota House of Representatives
  8. undated The Fine Print - Where Minnesota's Data Center Law Falls Short · CURE
  9. undated Minnesota Expands Data Center Sales Tax Program · Ryan LLC
  10. undated Data centers and the PUC's role · Minnesota Public Utilities Commission
  11. undated Regulatory Update - Commission approves Xcel Energy's large load tariff · Fresh Energy
  12. undated Farmington, Minn., Residents Sue to Stop Data Center Park · Government Technology
  13. undated Google scales back proposed data center in northeast Minnesota · Star Tribune
  14. undated Governor Walz Announces Meta Will Build New Data Center in Rosemount · Minnesota Department of Employment and Economic Development
  15. undated Electric Power Monthly, Table 5.6.B. Average Price of Electricity to Ultimate Customers by End-Use Sector, by State, Year-to-Date · U.S. Energy Information Administration

Last reviewed Sep 17, 2026