Stargate Saline Township (The Barn)
Under constructionMichigan · Washtenaw · last verified Sep 17, 2026
- Developer
- Related Digital (with Blackstone Real Estate)
- Tenant
- Oracle / OpenAI
- Location
- Saline Township, Washtenaw, Michigan
- Announced capacity
- 1.4 GW
- Capacity confidence
- Reported, partly confirmed
- Phase one
- —
- Site
- 575 acres
- Utility
- DTE Energy (MISO)
- Power source
- grid
- Reported investment
- $16B
- Announced
- Oct 18, 2025
- Target online
- —
Notes
DTE's filing describes 1.4 GW while Altman called it 'one gigawatt'; investment reported as $7B in Dec 2025 and $16B at June 2026 groundbreaking; three 550,000 sq ft buildings.
Location
Approximate coordinates: 42.1700, -83.7800 · open in OpenStreetMap
Sources
- Jun 1, 2026 OpenAI CEO Sam Altman, Whitmer visit Saline Township data center site · Detroit News
- Oct 18, 2025 Oracle is Set to Power on New Data Center in Michigan · Oracle
- undated Michigan regulators approve DTE's Saline data center contracts · Planet Detroit
See something wrong? Send a correction.