Project Marvel (Bessemer Hyperscale Data Center)
AnnouncedAlabama · Jefferson · last verified Sep 17, 2026
- Developer
- Logistic Land Investments LLC
- Tenant
- —
- Location
- Bessemer, Jefferson, Alabama
- Announced capacity
- 1.2 GW
- Capacity confidence
- Reported, partly confirmed
- Phase one
- —
- Site
- 1,607 acres
- Utility
- Alabama Power (Southern Company)
- Power source
- grid
- Reported investment
- $14.5B
- Announced
- Mar 18, 2025
- Target online
- Construction expected to take at least 7 years
Notes
18 buildings / 4.5M sq ft on 1,607 acres; court TRO halted April 2025 council vote; council amended zoning October 2025; rezoning status not confirmed.
Location
Approximate coordinates: 33.4000, -86.9500 · open in OpenStreetMap
Sources
- May 11, 2025 Alabamians Want Answers About a Four-Million-Square-Foot Data Center Coming to Their Backyards · Inside Climate News
- undated Bessemer Hyperscale Data Center · Bhamwiki