Project Jade / Cheyenne Power Hub (Switchgrass Industrial Park)
PermittedWyoming · Laramie · last verified Sep 17, 2026
- Developer
- Tallgrass Energy (Crusoe was original data center partner; reported to have exited in 2026)
- Tenant
- —
- Location
- Cheyenne, Laramie, Wyoming
- Announced capacity
- 1.8 GW
- Capacity confidence
- Reported, partly confirmed
- Phase one
- —
- Site
- 600 acres
- Utility
- —
- Power source
- on-site gas (2.7 GW BFC Power / Cheyenne Power Hub, incl. Bloom Energy fuel cells) plus future renewables
- Reported investment
- —
- Announced
- Jul 24, 2025
- Target online
- First buildings operational by mid-2027
Notes
Announced at 1.8 GW scalable to 10 GW; Laramie County approved site plans 2026-01-05; Crusoe reportedly left the project and Tallgrass continues. Tallgrass energy-hub investment reported at $7B (not recorded as project capex); Crusoe exit reported 2026-06-09; Tallgrass negotiating replacement partners.
Location
Approximate coordinates: 41.1400, -104.8200 · open in OpenStreetMap
Sources
- Jan 8, 2026 Wyoming Approves Data Center Campus That Includes 2.7 GW of New Natural Gas-Fired Generation · POWER Magazine
- Jul 24, 2025 Crusoe and Tallgrass Announce AI Data Center in Wyoming · Tallgrass Energy
- Jul 24, 2025 Crusoe and Tallgrass announce AI data center in Wyoming · Crusoe
- undated Crusoe pulls out of Project Jade data center · Wyoming Tribune Eagle