Project Jade / Cheyenne Power Hub (Switchgrass Industrial Park)

Permitted

Wyoming · Laramie · last verified Sep 17, 2026

Developer
Tallgrass Energy (Crusoe was original data center partner; reported to have exited in 2026)
Tenant
Location
Cheyenne, Laramie, Wyoming
Announced capacity
1.8 GW
Capacity confidence
Reported, partly confirmed
Phase one
Site
600 acres
Utility
Power source
on-site gas (2.7 GW BFC Power / Cheyenne Power Hub, incl. Bloom Energy fuel cells) plus future renewables
Reported investment
Announced
Jul 24, 2025
Target online
First buildings operational by mid-2027

Notes

Announced at 1.8 GW scalable to 10 GW; Laramie County approved site plans 2026-01-05; Crusoe reportedly left the project and Tallgrass continues. Tallgrass energy-hub investment reported at $7B (not recorded as project capex); Crusoe exit reported 2026-06-09; Tallgrass negotiating replacement partners.

Location

Approximate coordinates: 41.1400, -104.8200 · open in OpenStreetMap