Project Bluestem
RumoredKansas · Leavenworth · last verified Sep 17, 2026
- Developer
- Cloverleaf Infrastructure
- Tenant
- —
- Location
- Tonganoxie, Leavenworth, Kansas
- Announced capacity
- 1.2 GW
- Capacity confidence
- Estimate or generation figure
- Phase one
- —
- Site
- 1,000 acres
- Utility
- Evergy (Southwest Power Pool)
- Power source
- grid plus proposed on-site gas plant (revised plan)
- Reported investment
- —
- Announced
- Mar 18, 2025
- Target online
- —
Notes
Originally ~600 MW; September 2026 revised plan is 'up to 1.2 GW' with added gas plant; still conceptual with no applications filed.
Location
Approximate coordinates: 39.1100, -95.0900 · open in OpenStreetMap
Sources
- Sep 16, 2026 Tonganoxie neighbors brace as data center plan doubles its power demand · Hoodline
- Mar 18, 2025 Hyperscale data center proposed in Tonganoxie · KSHB 41
- undated Project Bluestem · Cloverleaf Infrastructure
See something wrong? Send a correction.