Nebius Vineland

Operating

New Jersey · Cumberland · last verified Sep 17, 2026

Developer
Nebius (build-to-suit; DataOne reported as building owner)
Tenant
Microsoft ($17.4B, 5-year GPU capacity deal)
Location
Vineland, Cumberland, New Jersey
Announced capacity
300 MW
Capacity confidence
Stated in primary source
Phase one
100 MW
Site
Utility
Power source
on-site fuel cells (per press reports)
Reported investment
Announced
Mar 5, 2025
Target online
100 MW installed by end of 2025; additional phases to follow

Notes

Nebius release does not name Vineland, DataOne or fuel cells; those come from secondary reporting. Status 'operating' assumes first phase online as planned; confirm.