Wired Real Estate
← Tracker

Microsoft Fairwater (Mount Pleasant)

Under construction

Wisconsin · Racine · last verified Sep 17, 2026

Developer
Microsoft
Tenant
Microsoft
Location
Mount Pleasant, Racine, Wisconsin
Announced capacity
450 MW
Capacity confidence
Estimate or generation figure
Phase one
Site
315 acres
Utility
We Energies (MISO)
Power source
grid
Reported investment
$3.3B
Announced
May 8, 2024
Target online
Early 2026

Notes

Capacity is an estimate from reporting, not a Microsoft figure; status may now be Operating.

Location

Approximate coordinates: 42.7200, -87.9300 · open in OpenStreetMap

Sources

See something wrong? Send a correction.