Compass Datacenters Meridian Campus

Under construction

Mississippi · Lauderdale · last verified Sep 17, 2026

Developer
Compass Datacenters
Tenant
Corderill LLC (partial tenant, $100M, announced April 2026)
Location
Meridian, Lauderdale, Mississippi
Announced capacity
500 MW
Capacity confidence
Reported, partly confirmed
Phase one
Site
Utility
Mississippi Power (Southern Company)
Power source
grid
Reported investment
$10B
Announced
Jan 9, 2025
Target online
Eight data centers built over eight years

Notes

Governor release says Mississippi Power will supply 'approximately 500 megawatts'; $10B includes future tenants' IT equipment.