CleanArc VA1 Data Center Campus

Under construction

Virginia · Caroline · last verified Sep 17, 2026

Developer
CleanArc Data Centers
Tenant
Location
Caroline, Virginia
Announced capacity
900 MW
Capacity confidence
Stated in primary source
Phase one
300 MW
Site
Utility
Power source
grid
Reported investment
$3B
Announced
Dec 1, 2025
Target online
First 300 MW Q1 2027; full buildout by 2035

Notes

VEDP announcement was November 2025 (exact day not confirmed); groundbreaking reported 2025-12-01.

Location

Approximate coordinates: 38.0300, -77.3500 · open in OpenStreetMap

Sources

  1. Dec 1, 2025 Data center developer breaks ground on $3B Virginia campus · Construction Dive
  2. undated CleanArc Data Centers Invests $3 Billion in Caroline County · Virginia Economic Development Partnership