Wired Real Estate
← States

Virginia

The world's largest data center market is now pushing south of Loudoun, under a new $0.011 per kWh electricity tax, a 14-year large-load tariff, and county-level zoning fights.

Tracked projects
3
Announced capacity
3 GW
Grid operator
PJM
Sales tax exemption
Yes

Why developers come here

Northern Virginia is where the modern data center industry grew up. Loudoun County’s “Data Center Alley” sits on the densest fiber interconnection point in the country, next to the federal government and its contractors, inside PJM’s wholesale market. That network effect is why operators keep building here even as land, power, and politics get harder.

The 2024 JLARC study, the most thorough public accounting of the industry in any state, estimated data centers support about 74,000 jobs and $9.1 billion of Virginia GDP a year, most of it during construction. It also found that unconstrained electricity demand in Virginia would roughly double within ten years, driven mainly by data centers, and that a typical Dominion residential customer could see generation and transmission costs rise $14 to $37 a month by 2040 unless cost allocation changes.

Power is the constraint. Virginia’s industrial rate averaged 10.08 cents per kWh through June 2026 per EIA, up from 9.18 cents a year earlier, and PJM capacity prices for 2026/27 cleared at the $329 per MW-day cap. Developers now go south and west for land and interconnection slots rather than waiting in Loudoun.

Incentives

Power

Virginia is in PJM, so new generation and large loads go through PJM’s interconnection queue and Dominion’s transmission planning. Dominion Energy Virginia serves Northern Virginia and most of the east; Appalachian Power serves the southwest; cooperatives such as NOVEC serve pockets of Loudoun and Prince William.

The State Corporation Commission’s November 2025 order in Dominion’s biennial review (Case PUR-2025-00058) created the GS-5 rate class for customers with 25 MW or more of demand at high load factor, effective January 1, 2027. New GS-5 customers sign 14-year contracts, pay at least 85 percent of the transmission and distribution capacity charge and 60 percent of generation charges each month regardless of usage, post collateral, and must give years of notice to reduce contracted demand. Consumer advocates wanted 20-year terms. The SCC also approved a $775.6 million rate increase, adding about $16 a month to the typical residential bill.

Dominion’s queue is long: industry summaries describe roughly 70 GW of requests with about 25 GW assigned connection dates through 2031. Delivery dates in Loudoun have stretched years out, which is the main reason activity has moved to Louisa, Caroline, Stafford, Spotsylvania, Culpeper, Pittsylvania, and Mecklenburg counties, where transmission is available and localities are recruiting.

Where the projects are

Loudoun, Prince William, and Fairfax remain the core. The growth ring runs down I-95 and US-29 and into Southside. Tracked projects include EdgeCore’s Louisa County campus, CleanArc’s VA1 campus in Caroline County, and STACK’s Stafford Technology Campus. Culpeper’s technology zone has attracted AWS, CloudHQ, EdgeCore, and others. Land in the Prince William data center corridor has traded near $1 million an acre, and Loudoun industrial land has gone higher.

Local politics

Loudoun ended by-right data center development on March 18, 2025 by a 7-2 vote; every new project now needs a special exception with public hearings, though about 22 pending applications were grandfathered. Prince William’s 2,100-acre Digital Gateway, approved in 2023 next to Manassas National Battlefield, was voided by the circuit court in August 2025 over defective public notice, affirmed by the Court of Appeals on March 31, 2026, and abandoned when QTS dropped its Supreme Court appeal in July 2026. Both fights were about noise, diesel generators, viewsheds, transmission lines, and the sense that residents were not consulted.

Southside and Piedmont counties have generally welcomed projects for the tax base, sometimes with revenue-sharing or reduced equipment tax rates, though Culpeper and Louisa have each seen contested rezonings. Statewide, the 2026 session showed both parties willing to tax and condition the industry while stopping short of ending the exemption.

What a landowner should know

Outside Northern Virginia, developers are looking for 300 to 1,500 acres near existing 230 kV or 500 kV transmission, ideally with an existing or planned Dominion substation, flat topography, and access to water and sewer or the ability to build closed-loop cooling. Option agreements with 18 to 36 month diligence periods are standard because the Dominion and PJM interconnection timeline drives everything. Ask whether the developer has a PJM queue position or a Dominion large-load study underway.

Localities now control the pace. Check the county’s zoning for data centers, any technology zone incentives, and whether HB 153 sound assessments apply. The state contact is the Virginia Economic Development Partnership, which administers the exemption MOU; the SCC posts large-load rulings and Dominion’s tariffs.

Tracked projects in Virginia

Project Location Developer Capacity Status Announced Verified
EdgeCore Louisa County campus Louisa, VA EdgeCore Digital Infrastructure 1.1 GW Announced Jun 25, 2025 Sep 17, 2026
STACK Stafford Technology Campus Stafford, VA STACK Infrastructure 1 GW Announced Jan 16, 2025 Sep 17, 2026
CleanArc VA1 Data Center Campus Caroline, VA CleanArc Data Centers 900 MW Under construction Dec 1, 2025 Sep 17, 2026

Sources

Last reviewed Sep 17, 2026