Georgia

The Southeast's busiest hyperscale market, with a tiered sales tax exemption that survived repeal votes in 2024 and 2026 and a PSC that now vets every 100 MW contract.

Tracked projects
4
Announced capacity
4.1 GW
Grid operator
Non-ISO (Southern Company)
Sales tax exemption
Yes

Why developers come here

Georgia has become the Southeast’s default answer to “where else besides Virginia.” Metro Atlanta was already a major fiber and colocation hub, and the state combines that with large tracts of rural land within reach of Georgia Power’s transmission system, a vertically integrated utility that has committed to build generation for large customers, and a state sales tax exemption on data center equipment that the legislature has tried and failed to repeal twice.

The scale of what is being asked for is unusual. Georgia Power told regulators in November 2025 that its pipeline of large-load projects stood at about 50.9 GW through the mid-2030s, with 28 committed projects representing about 11 GW and 18 of them under construction. Regulatory staff also noted that 33 data center projects totaling more than 11,000 MW had dropped out since 2023, so the pipeline is large but not firm.

Industrial power averaged 7.62 cents per kWh in Georgia through June 2026 according to EIA’s Electric Power Monthly, well below Virginia.

Incentives

Power

Georgia is not in an ISO. Georgia Power, a Southern Company subsidiary, is the dominant vertically integrated utility; the electric membership cooperatives (supplied by Oglethorpe Power) and municipal systems (MEAG Power) serve much of rural Georgia. Interconnection is a bilateral negotiation with the utility, and the PSC approves the generation the utility builds to serve new load.

In January 2025 the PSC adopted rules, effective February 1, 2025, for customers of 100 MW or more. Each such customer must sign a customized contract rather than take a standard tariff. Contracts can run up to 15 years, may include minimum bills that are owed regardless of actual usage, may require upfront infrastructure payments and financial guarantees, and must be filed with the PSC for review before signing. Georgia Power filed its first roughly 2 GW of contracts under the rules in September 2025. In August 2026 PSC staff approved the service agreement for OpenAI’s Project Camellia near Savannah, reported at 3,200 MW firm, though the financial terms were largely redacted.

On the supply side, the PSC approved Georgia Power’s 2025 Integrated Resource Plan in July 2025, forecasting roughly 8,500 MW of load growth over six years, mostly from data centers, and keeping coal units at Plants Bowen and Scherer running longer than planned. A separate certification of nearly 10 GW of new capacity followed. Consumer and environmental groups argue residential customers are exposed if the forecast load does not show up; the utility and PSC say the minimum-bill contracts shift that risk to the data centers.

Where the projects are

Activity clusters in three bands: the metro Atlanta ring (Douglas, Coweta, Fayette, Clayton, DeKalb, Bartow, and Butts counties), the I-85 and I-75 corridors north and south of the city, and the Savannah area. Tracked projects include Project Camellia (OpenAI, Effingham County), Project Sail (Atlas Development, Coweta County), AWS campuses in Butts and Douglas counties, Microsoft’s Fairwater Atlanta, and the QTS and Lancium campus in Hall County.

Local politics

Georgia has seen one of the fastest local backlashes in the country. GPB counted eight jurisdictions that adopted temporary moratoria between March and October 2025, including Coweta, Pike, Lamar, Troup, and Clayton counties and the City of LaGrange, and several more have followed, among them DeKalb, Douglas, Dougherty, Walker, and the City of Fayetteville. Counties that kept the door open wrote ordinances instead: Bartow set 200-foot buffers and 55 to 65 decibel noise limits, Jones requires closed-loop cooling, Forsyth bars use of county water for cooling, and Atlanta banned data centers near the Beltline.

The objections are consistent: water use and its source, noise, construction blasting and well damage reported by neighbors of the Meta campus in Newton County and the AWS site in Social Circle, farmland conversion, and the question of who pays for new power plants. Coweta’s Project Sail drew a 1,750-signature petition and a legal appeal from neighbors before it was permitted.

Supporters point to the property tax base: county commissions have approved bond-lease abatements on the argument that even a discounted payment from a multibillion-dollar campus dwarfs existing revenue, and state officials continue to recruit hyperscalers.

What a landowner should know

Hyperscale campuses in Georgia are running 500 to more than 1,000 acres, and the first question a site selector will ask is distance to a Georgia Power 230 kV or 500 kV line or an existing substation. Under the 2025 PSC rules the developer, not the landowner, negotiates the power contract, and that process can take a year or more, so option agreements with long due-diligence periods are the norm. Check whether the parcel is in Georgia Power territory or an EMC’s; both can serve large loads but the process and timeline differ.

Local zoning now matters as much as state policy. Before signing, confirm whether the county has a moratorium, a data center overlay, or new setback and noise rules, because many were adopted in 2025 and 2026. The state contact is the Georgia Department of Economic Development, and the sales tax certificate is issued by the Georgia Department of Revenue. Counties post the aggregate exemption spending by county, which is a useful signal of where activity already is.

Tracked projects in Georgia

Project Location Developer Capacity Status Announced Verified
Project Camellia (OpenAI Savannah-area campus)
for OpenAI
Effingham, GA OpenAI 3.2 GW Announced Jul 22, 2026 Sep 17, 2026
Project Sail (Atlas Development) Coweta, GA Atlas Development, LLC 900 MW Permitted Jan 5, 2025 Sep 17, 2026
AWS Georgia (Butts and Douglas Counties)
for AWS
Butts / Douglas, GA Amazon Web Services Announced Jan 7, 2025 Sep 17, 2026
Microsoft Fairwater Atlanta
for Microsoft
GA Microsoft Operating Nov 12, 2025 Sep 17, 2026

Sources

  1. Aug 17, 2026 Will the New OpenAI Data Center Raise Georgia Power Bills? · Southern Alliance for Clean Energy
  2. Apr 3, 2026 Data Center Break Survives Georgia Income, Property Tax Push · Bloomberg Tax
  3. Mar 7, 2026 Georgia Senate votes to claw back data center tax breaks · Atlanta Journal-Constitution
  4. Feb 19, 2026 Georgia General Assembly Proposes Bills to Curb Sales Tax Exemptions Used by Data Centers · Alston & Bird
  5. Nov 24, 2025 Georgia Power's large load pipeline shrinks by 6 GW · Utility Dive
  6. Oct 31, 2025 Southern inks 7 GW of large load contracts, eyes 50 GW more · Utility Dive
  7. Oct 22, 2025 A 'wave' of data center ordinances sweep through GA counties. How strict are they? · Georgia Public Broadcasting
  8. Sep 30, 2025 Georgia Power highlights first contracts under new rules and regulations, continued economic growth and updated forecasts in latest filings with Georgia PSC · Georgia Power
  9. Jan 23, 2025 PSC Approves Rule to Allow New Power Usage Terms for Data Centers · Georgia Public Service Commission
  10. May 9, 2024 Georgia lawmakers vowed to restrain tax breaks. But the governor's veto saved a data-center break · Georgia Public Broadcasting
  11. undated Data Centers Sales & Use Tax Exemption - Aggregate Expenditures by County · Georgia Department of Revenue
  12. undated Georgia sales and use tax exemption for AI data centers · Compute Law Blog
  13. undated Georgia property tax and local tax breaks for AI data centers · Compute Law Blog
  14. undated Electric Power Monthly, Table 5.6.B. Average Price of Electricity to Ultimate Customers by End-Use Sector, by State, Year-to-Date · U.S. Energy Information Administration

Last reviewed Sep 17, 2026